New play space by the recreation ground (March-June 2020)

Update 24/3/2020.  Due to the Coronavirus outbreak we have had to postpone the start date for the play space works.  We will deliver this project as soon as the situation allows.

Update: 4/2/2020.  The contractor has postponed the start date as they are running behind on some other projects due to the 3 recent major storms.  Work will now take place between the end of March and early June.

 

The removal of the old play equipment from the recreation ground will commence at the beginning of March 2020 and will be followed by the installation of the new play equipment from Huck.  Works should be complete by the end of May or early June.

The site compound will be located in the car park at the rear of the Memorial Hall, which will reduce parking capacity during this period.  Please bear with us whilst works are in progress.

Play areas will still be available in Windsor Road and Hever Close.  We look forward to opening the exciting new play space once works are complete.