Westfield Road / Castlemead remedials 23/12/21 (& 10/1/22 update)

10/1/22: Taylor Wimpey have advised Buckinghamshire Council that works are a few days behind schedule but they hope to be complete by Friday 14/1/22.

Taylor Wimpey’s contractors are behind schedule. Their original target to complete the remedial works to Westfield Road and the residential areas had been by 24/12/21. Earlier in their works schedule, they had hoped to complete ahead of schedule by 17/12/21. The works to the residential roads have yet to be completed, and therefore they have not yet moved out to undertake the remedial works to Westfield Road.

Taylor Wimpey has now arranged a new completion date (weather permitting) with Buckinghamshire Council of 10 January 2022. Taylor Wimpey’s contractors are now on Christmas shut down, and due to return from 4 January 2022.

(Note that the current phase of remedials/adoption does not include the final phase of the residential area of Castlemead, nor the business park, both of which will follow at a later date.)

Attachment(s):

    The owner of this website has made a commitment to accessibility and inclusion, please report any problems that you encounter using the contact form on this website. This site uses the WP ADA Compliance Check plugin to enhance accessibility.